<< Show table of contents >> Programmes > Opened programme > Fundings > Programme fundings > General |
To create a new funding or to edit an existing one, complete the fields in the individual sections and click on Save.
NOTE: Programme fundings are not explicitly recorded when posting. Instead, you must create project fundings in the projects of a programme and assign them to a programme funding. |
Form of funding |
The form of funding distinguishes between project funding and programme funding. |
|||||||||||
Project |
Enter the project for which a funding is to be created.
|
|||||||||||
Programme |
Enter the programme for which a funding is to be created.
|
|||||||||||
Funding |
Give the funding a unique name. The name of the funding is shown in WINPACCS Cloud, WINPACCS Accounting and WINPACCS Cashbook wherever a funding can be selected. |
|||||||||||
A funding contract passes through different statuses. Depending on the contract status, you must enter certain information in the master data. The contract status determines whether costs can be assigned to the funding in WINPACCS Accounting, WINPACCS Cashbook and in Project controlling, and which functions are available. You can change the contract status to a higher status and skip statuses. But it is not possible to switch to a lower status. However, you can undo changes, as long as they have not yet been released. |
||||||||||||
In planning |
The funding is in the planning stages and there is not yet a contract with a donor. At this stage, you cannot release the funding or assign it to any journals. Therefore, it is not yet possible to assign costs to the planned funding or to create a budget for it. |
|||||||||||
Applied for |
The funding of the project has been applied for at the donor. You can release the funding and assign it to journals. Once the funding is assigned to one or more journals, you can assign postings to it and create budgets for it. |
|||||||||||
Approved |
The funding was approved by the donor. You can no longer change the funding period; it can only be extended. |
|||||||||||
Finalised |
The funding is finalised. The total amount was disbursed and spent. You cannot assign any new journals to the funding. |
|||||||||||
Finally calculated |
The contract has ended. The settlements with the donor have been fully verified. No more postings or repostings are performed. No new vouchers can be assigned to the funding. |
|||||||||||
Programme funding |
Indicate to which programme funding the project funding is assigned.
|
|||||||||||
Type of funding |
Specify what type of funding it is. If the funding consists of own funds, select a type from this list and, select your own organisation in the next field (Donor). Donors are created in the Donor management functional area.
|
|||||||||||
Funds from |
Indicate here whether the funding is received from a partner or a donor.
|
|||||||||||
Donor |
Select the donor of the funding. Donors are created in the Donor management functional area.
|
|||||||||||
Title of donor |
If the donor has various titles, select the appropriate title for this funding here.
|
|||||||||||
Partner |
Select the Partner of the funding. Partner are created in the Partner management functional area.
|
|||||||||||
Date of approval |
Enter the date on which the contract was signed by the donor. The duration is independent of this and is entered further below. |
|||||||||||
Internal contract number |
Enter the number of the funding contract assigned by your own organisation. |
|||||||||||
External contract number |
Enter the number of the funding contract assigned by the donor. |
|||||||||||
Grand total |
Enter the grand total approved by the donor and specify the currency. The amount is for information only and is not used for calculations in Project controlling.
|
|||||||||||
Select whether the funding applies to the entire project or programme period or specify a shorter period. The period must be within the project or programme period. If the project funding is assigned to a programme funding, the period must also be within the period of the programme funding. Once the contract status has been set to Approved you can no longer change the period of the funding; you can only extend it within the project or programme period. To specify an even longer period, you must first extend th the project or programme duration. |
||||||||||||
Comment on master data |
Use this field for additional information on this funding. |
|||||||||||
Comment funding |
Use this field for additional information on donor requirements. |
|||||||||||
Comment on reporting |
Use this field for instructions about reporting, such as reporting currency or rate requirements. |
|||||||||||
Postable when the project is posted to as an external project |
This setting determines whether other projects are allowed to assign vouchers to this funding if costs are incurred for this project. If you do not select this option, the funding is not available if other projects post to this project as an external project.
|
NOTE: If further fields are available, they are individual fields. These fields can be used to collect additional data on the funding that could not otherwise be collected in WINPACCS Cloud. Which fields are Included and whether they are mandatory fields is defined in the organisational settings. |
The donor’s contact for this funding can be selected here. You define which persons are available for the donor in the Donor management functional area.
The Table shows all the project fundings assigned to the programme funding. Above the table, the total amount of the programme funding is also compared with the total amount of all assigned project fundings.
Double-click on an entry to open the selected project funding.
NOTE: The amounts serve for information only and are not used for calculations in Controlling. |
Edit |
Switches to the edit mode. Note that the Contract status and the Organisational settings affect which fields are available or are mandatory. |
|
Creates a PDF document that displays the funding data. |
||
Delete |
Deletes the funding. Only available for fundings with the Contract status In planning, as these have not yet been assigned to a posting. |
|
Archive |
Archives the funding. It remains assigned to journals and postings, but is no longer available in the fundings overview and cannot be assigned to any new project funding. Only available for fundings with one of the Contract statuses Applied for, Approved, Completed or Finally invoiced to which no non-archived project fundings are assigned. Use the quick filter Display archived programme fundings ( |
|
Save |
Saves the changes. |
|
Cancel |
Switches to the display mode without saving changes. |